5/28/07                    Press Release

Sundial Center Rebuilding Process Moving Forward; RCSC Awaiting Final Permit from Maricopa County

At the Recreation Centers of Sun City, Inc., Director/Member Exchange meeting on Monday, May 21, Assistant General Manager Jim Wellman reported on the progress of the rebuilding of Sundial Recreation Center. Mr. Wellman explained that RCSC is waiting to receive a permit from Maricopa County but has already hired a contractor and is working out the final details of the project as well as the schedule. The pool, spa and fitness center at Sundial, as well as several club rooms, have been closed nearly a year since the roof over the indoor pool collapsed in June 2006. 

RCSC filed a building permit request with Maricopa County in mid-February and submitted a set of building plans for approval by the county. The county returned those plans with some required changes in late March, a very fast turnaround time due to an appeal from RCSC to expedite the permitting process. RCSC resubmitted the plans to the county at the end of April. On May 23, the county came back with a few more required changes to the plans. The project architects are working on the corrections and expect to resubmit the plans for final approval shortly. 

The Weitz Company has been hired as the general contractor and building manager for the project. Mr. Wellman reported that RCSC is finalizing the contract with Weitz and determining the project schedule. 

When asked by a cardholder whether the Sundial pool was damaged in the roof collapse, Mr. Wellman explained that, based on an inspection by a certified pool engineer, the bond beam around the pool had not been cracked so the pool structure itself was intact. He noted that the pools and spas will probably require refinishing and the decking will also need to be replaced due to damage incurred as a result of the collapse as well as necessary construction traffic. 

Structural engineers examining the entire building have also discovered hidden damage outside the pool area that will increase the scope of the project. The cost to repair this damage will be an addition to the cost of repairing the roof and pool area. Investigation is continuing and actual cost figures are being sought.

Contact: Lindsay Frost, RCSC Communications Coordinator (623) 876-3060, ext. 3087; lfrost@sunaz.com.