| 8/30/2010 | Lakeview Installation Complete! | |
| 8/27/2010 | Lanes, approaches, kickbacks and flat gutters installed, cleanup begins on 8/28/2010 | |
| 8/26/2010 | Lanes installed, finishing approaches and beginning to reinstall ball racks, foul lights etc. | |
| 8/20/2010 | New panels installed lanes 1-16, beginning to install new panels on lanes 17-24 | |
| 8/16/2010 | New lane panels being installed | |
| 8/13/2010 | Problem solved with approach hump between 16 & 17. Shims removed and approach will be flat. | |
| 8/12/2010 | Dan Will bowled the 1st 300 Game on the new lanes at Bell ! | |
| 8/11/2010 | New underlayment ( LSL) being installed lanes 1-16 | |
| 8/04/2010 | Approaches and first 10' of lane to be removed and replaced with LSL | |
| 8/02/2010 | All old lanes and approaches removed. Prep work begins | |
| 7/29/2010 | 17-24 Kickbacks removed and replaced. | |
| 7/28/2010 | Lakeview Lanes closed for remainder of installation | |
| 7/27/2010 | Lanes 15-24 - old lanes and approaches being removed. | |
| 7/26/2010 | Materials delivered to Lakeview lanes | |
| 7/24/2010 | Bell Lanes Project complete | |
| 7/23/2010 | Final cleanup in progress | |
| 7/22/2010 | Final cutting on new panels... Cleanup begins! | |
| 7/20/2010 | All Lanes installed. Installers in process of trimming approaches and installing fill panels | |
| 7/16/2010 | 8 lanes of new panels installed. | |
| 7/12/2010 | Final sanding in progress, new panels scheduled to be installed Wednesday 7/14/10 | |
| 7/08/2010 |
8 Lanes of flat gutters and kickbacks installed Old lane surface leveled and ready for laminate |
|
| 7/07/2010 |
8 lanes of kickbacks installed, RCSC Mechanics began adjusting Pinsetters to Brunswick Specs |
|
| 7/03/2010 | Bell Lanes closing for remainder of installation | |
| 7/02/2010 | Installation of kickbacks begins | |
| 7/01/2010 | 8 Lanes of Synthetics removed, contractor is preparing surface to install new synthetic lanes and beginning to install new kickbacks | |
| 6/30/2010 | Began removal of old lanes and approaches at Bell Lanes | |
| 6/29/2010 | Materials Delivered To Bell Lanes |